GE Aerospace has reportedly dispatched the 15th F404-IN20 engine for India’s Tejas Mk1A fighter programme, offering a sign of movement in a project that has faced repeated delays. The Indian Air Force (IAF) expects to induct its first Tejas Mk1A squadron by the end of March 2027, according to details reported by The Statesman.
The latest dispatch comes after Air Chief Marshal Ashutosh Dixit said that the first squadron would join the IAF within the current financial year. Speaking at a media summit in New Delhi, the Chief of the Air Staff said:
“Very shortly, we will have LCA [Tejas] Mk1A joining [the] Indian Air Force. Within this financial year, we will have a squadron. Then we will continue developing; we will take it further.”
Air Chief Marshal Ashutosh Dixit also said that the LCA Mark-2 could roll out “maybe next year” and that work was continuing on the Advanced Medium Combat Aircraft (AMCA) programme. His remarks place the Mk1A induction target within a wider effort to expand India’s indigenous fighter-aircraft pipeline.
Engine supply remains central to the schedule
Hindustan Aeronautics Limited had initially planned to begin handing over the first batch of 83 Tejas Mk1A aircraft in February 2024. Delivery plans were affected primarily by delays in obtaining the F404-IN20 engines from GE Aerospace. HAL signed an agreement with the US company in 2021 for 99 engines, but the first powerplant under that arrangement arrived only in March 2025.
GE Aerospace attributed the delay to supply-chain disruption and difficulties involved in restarting production. At a media summit in September, Defence Secretary Rajesh Kumar Singh said India could receive approximately 22 engines by the end of 2026, following GE’s commitment to supply four engines each month from October. He described the pace of deliveries as “not good enough”.
| Programme detail | Figure or timeline |
|---|---|
| F404-IN20 engine dispatched | 15th engine |
| Engine agreement with GE Aerospace | 99 engines, signed in 2021 |
| Initial Tejas Mk1A order | 83 aircraft |
| Additional IAF order | 97 aircraft, September 2025 |
| Expected first IAF squadron | By the end of March 2027 |
HAL has completed airframes while awaiting powerplants
Rajesh Kumar Singh said HAL had completed 27 aircraft airframes. Of these, 11 had been fitted with engines, while the remaining 16 had undergone testing with reserve engines pending the arrival of their designated powerplants. The figures illustrate how engine availability has become a determining factor in converting completed airframes into aircraft ready for delivery.
The IAF has placed orders for 180 Tejas Mk1A fighters: an initial contract for 83 aircraft and a subsequent order for 97 aircraft in September 2025. The pace at which the F404-IN20 engines arrive will therefore remain closely linked to the service’s ability to receive aircraft under both orders and to establish the first Mk1A squadron within the stated March 2027 target.